Analisis Keandalan Sistem Distribusi 20 KV dari GI Industri Penyulang I.5 Sampai Dengan Gardu Hubung Rapak

Tri Teguh Setiawan, A. Asni B, Bambang Sugeng

Abstract


The reliability of the electric power distribution system can be seen from the SAIDI number (System Average Interruption Duration Index) or long extinguished in one period and SAIFI (Sytem Average Interruption Frequency Index) or outages in one period. PT PLN (Persero) Balikpapan Area is currently trying to improve service used reliability improvement methods, namely by maneuvering the radial system network load into a loop system network and installing reclosers. Penyulang Industri 5 (I.5) for 2017 has SAIDI realization value of 7.741 hours / year, and SAIFI is 5.03 times / year. It can be interpreted that SAIDI-SAIFI 5 industrial feeders are relatively few of the value of the revised targets. This shows that industrial feeder 5 has a high level of reliability. But it still does not meet the IEEE Std standard. 1366-2000 with a SAIDI score of 2.30 hours / year and a SAIFI value of 1.45 times / year. After the improvement is obtained the value of SAIDI is almost close to the IEEE Std standard value. 1366-2000 which is 2,365 hours / year.

Keywords : Reliability, SAIDI/SAIFI, Load Manuver, Recloser.

 


Keywords


Reliability; SAIDI/SAIFI; Load Manuver; Recloser

Full Text:

PDF

References


P. P. (Persero) P. P. dan P. Pusat Penelitian dan Pengembangan Ketenagalistrikan, Kriteria Disain Enjinering Konstruksi Jaringan Distribusi Tenaga Listrik, 1st ed. Jakarta: PT PLN (PERSERO), 2010.

G. R. A. Y. Hardiyanti, “Perbaikan Tegangan Pada Jaringan Tegangan Menengah Penyulang Pakis di Gardu Induk Menggala Provinsi Lampung,” Sekolah Tinggi Teknik-PLN, 2017.

J. M. T. Haryono et al., “Analisis Keandalan Sistem Distribusi Tenaga Listrik Penyulang Jember Kota dan Kalisat di PT PLN APJ Jember,” pp. 1–9.

Erhaneli, “Evaluasi Keandalan Sistem Distribusi Tenaga Listrik Berdasarkan Indeks Keandalan SAIDI dan SAIFI pada PT PLN (Persero) Rayon Bagan Batu Tahun 2015,” J. Tek. Elektro ITP, vol. 5, no. 2, pp. 120–129, 2016.

F. Yusuf Ridho Surya Dharma Nainggolan, “Analisis Keandalan Berbasis Sistem pada Jaringan Distribusi 20 kV UPJ PT PLN (Persero) Area Pekanbaru Rayon Panam,” Jom FTEKNIK, vol. 3, no. 2, pp. 1–9, 2016.

A. Fatoni, R. S. Wibowo, and A. Soeprijanto, “Analisa Keandalan Sistem Distribusi 20 kV PT . PLN Rayon Lumajang dengan Metode FMEA ( Failure Modes and Effects Analysis ),” J. Tek. ITS, vol. 5, no. 2, pp. 462–467, 2016.

A. Basrahpulungan, “Keandalan Jaringan Tegangan Menengah 20 Kv Di Wilayah Area Pelayanan Jaringan ( APJ) Padang PT . PLN ( Persero ) Cabang Padang,” J. Nas. Tek. Elektro, vol. 1, no. 1, pp. 58–61, 2012.

R. Saputra, “Analisa Nilai Indeks Keandalan Sistem Jaringan Distribusi Udara 20 kV pada Feeder PT . PLN ( Persero ) Rayon Sungai Penuh - Kerinci,” J. Tek. Elektro ITP, vol. 6, no. 1, pp. 93–98, 2017.

P. U. L. Negara, “Standar Keandalan Pada Sistem Distribusi 20 kV dan 6 kV,” SPLN 59: 1985, 1985.

W. P. Perdana, R. N. Hasanah, and H. S. Dachlan, “Evaluasi Keandalan Sistem Tenaga Listrik Pada Jaringan Dsitribusi Primer Tipe Radial Gardu Induk Blimbing,” J. EECIS, vol. III, no. 1, pp. 6–12, 2009.

A. T. Prabowo, I. B. Winardi, M. Kom, and S. Handoko, “Anaisis Keandalan Sistem Distribusi 20 kV pada Penyulang Pekalongan 8 Dan 11,” J. Tek. Elektro UNDIP, vol. 1, no. 2, pp. 1–8, 2013.

N. Hidayah, A. B. Muljono, and Supriyatna, “Analisis Manuver Jaringan Terhadap Keandalan Kontinuitas Penyaluran Tenaga Listrik Penyulang di Area Ampenan,” Dielektrika, vol. 3, no. 1, pp. 109–115, 2014.

K. K. S. K. D. J. T. L. Dan and P. P. S. dan T. U. Indonesia, Standar Konstruksi Jaringan Tegangan Menengah Tenaga Listrik, 1st ed. Jakarta: PT PLN (PERSERO), 2010.




DOI: https://doi.org/10.32487/jtt.v6i2.510

Refbacks

  • There are currently no refbacks.


JTT (Jurnal Teknologi Terpadu) has been indexed by:

 

 

 

 

 

 

 

 

 

Web
Analytics

JTT Visitor Stats