PERUBAHAN METODE PELAKSANAAN PEKERJAAN BETON IN SITU MENJADI METODE PRECAST
Abstract
Proyek Pembangunan Sulfur Jetty dan Pekerjaan Dredging TUKS Migas Proyek RDMP RU V
Balikpapan berlokasi Kota Balikpapan, Kalimantan Timur. Pada proyek ini terdapat 2 (dua)
lingkup pekerjaan utama, yaitu pekerjaan sulfur jetty dan pekerjaan dredging. Seperti proyek-
proyek lain, pada proyek ini dilakukan review engineering terhadap gambar desain, volume
pekerjaan, metode pekerjaan dan juga termasuk jadwal pekerjaan. Tujuan dilakukan review
engineering ini untuk mengevaluasi apakah perubahan metode pelaksanaan pada pekerjaan beton
In Situ menjadi Precast ini dapat memaksimalkan pekerjaan sesuai dengan konsep mutu, waktu
dan biaya. Untuk itu di lakukan pengajuan perubahan tersebut kepada Pertamina disertai
beberapa alasan teknis yang mempengaruhi pekerjaan tersebut. Untuk perubahan metode tersebut
dilakukan beberapa proses seperti pengajuan perubahan desain, perubahan metode kerja, proses
perhitungan struktur dan beberapa hal lainnya yang terkait dengan mutu dari struktur akibat dari
perubahan metode pelaksanaan. Dari hasil perhitungan struktur telah menyesuaikan dengan
kebutuhan sesuai dengan rencana awal, dengan merubah metode pemasangan namun tetap
menjaga kekuatan struktur sesuai dengan rencana awal. Dengan metode Precast ini maka proses
konstruksi relatif lebih aman dan terukur dari segi biaya dan waktu.
Kata kunci: perubahan metode kerja, perubahan desain, Precast, In Situ, jetty
CHANGES TO THE IMPLEMENTATION OF CONCRETE IN SITU WORK
METHOD BECOME A PRECAST METHOD
Sulfur Jetty Development Project and TUKS Migas Oil and Gas Dredging Project The RU V
Balikpapan RDMP Project is located in Balikpapan City, East Kalimantan. In this project there are
2 (two) main work scopes, namely sulfur jetty work and dredging work. Like other projects, an
engineering review of the design drawings, work volumes, work methods, and work schedules is
also carried out. The purpose of this engineering review is to evaluate whether the change in the
method of implementation of concrete works in Situ to Precast can maximize the work in
accordance with the concepts of quality, time and cost. For this reason the submission of the
amendment to Pertamina was accompanied by several technical reasons that affected the work. For
the method change, a number of processes were carried out such as the submission of design
changes, changes in work methods, the process of calculating the structure and several other
matters related to the quality of the structure due to changes in the method of implementation. From
the results of the calculation of the structure has adjusted to the needs in accordance with the initial
plan, by changing the installation method but still maintaining the strength of the structure in
accordance with the initial plan. With this Precast method, the construction process is relatively
safer and measurable in terms of cost and time.
Keywords: changes in work methods, changes in design, Precast, In Situ, jetty.
Full Text:
PDFReferences
F. Cahyono, “Study Perbandingan Proyek Pembangunan Gedung Metode Pelaksanaan Precast Dengan Metode Konvensional Dilihat Dari Segi Waktu Dan Biaya (Study Kasus Proyek Asrama Balai Sungai Surakarta Teknologi N- Panel System), Universitas
Tim proyek, Perhitungan Struktur JettySulfur, 2020
Tim proyek, Prosedur Pekerjaan Produksi Headstock, beam dan Slab Jetty Sulfur(Adhimix), 2020
Tim proyek, Prosedur Pekerjaan Produksi Headstock, beam dan slab jetty sulfur(APB), 2020
Tim proyek, Metode Pekerjaan HandlingMaterial Precast, 2020
Tim Proyek, Metode Pekerjaan Struktur Atas, 2020